BUDGET STATUS
Road and Other Infrastructure
-
350350

PROJECT: Rehabilitation of poor conditions barangay roads in the municipality of Payao
PROVINCE: ZamboangaSibugay
SITE: Minundas (1.5km)
Payabo-Dalama-
Labatan (5km)
Nanan-Binangonan (3km)
Upper Sumilong (2km)
PROJECT COST: Php6,670,000.00
FUNDS RELEASED: Php6,670,000.00
DATE RELEASED: September 13, 2011; September 27, 2012
STATUS OF IMPLEMENTATION: Completed; rehabilitation and regravelling of barangay roads completed
-
303150

PROJECT: Rehabilitation of poor conditions barangay roads in the municipality of Tungawan
PROVINCE: ZamboangaSibugay
SITE: Lower Tungawan (3km)
Sto. Nino (1.6km)
San Vicente (1.8km)
Tigbucay (1.8km)
DatuTumanggon (3km)
PROJECT COST: Php6,670,000.00
FUNDS RELEASED: Php5,340,000.00
DATE RELEASED: September 13, 2011
STATUS OF IMPLEMENTATION: Implementation Phase: Pre-construction meeting was held with the LGUs and posting at PHILGEPs completed in November; Earthworks and graveling on-going; Pouring of cement on-going; Billboard installed
-
460380

PROJECT: Rehabilitation of barangay roads in the municipality of Mabuhay
PROVINCE: Zamboanga Sibugay
SITE: Barlac-Sto. Nino (4km)
Sioton-Barlac (3km)
Galiran-S. Bomba (3km)
PROJECT COST: Php6,600,000.00
FUNDS RELEASED: Php6,600,000.00
DATE RELEASED: September 13, 2011; 27 September 2012
STATUS OF IMPLEMENTATION: Completed; Rehabilitation and regravelling of barangay roads completed.
-
242199

PROJECT: Water Supply System Level II
PROVINCE: Zamboanga Sibugay
SITE: Brgy. Datu Tumanggong
PROJECT COST: Php 2, 250, 000.00
FUNDS RELEASED: Php 2, 000, 000.00
DATE RELEASED: February 2012
STATUS OF IMPLEMENTATION: Implementation Phase; Construction delayed due to bad weather conditions and consequent delivery problems because of inaccebility roads leading to the project site, Unstable peace and order condition in the project site. -
242199

PROJECT: Rehabilitation of Datu Tumanggong-Sitio Sapa Mayaba-Guinacutan Brgy. Road
PROVINCE: Zamboanga Sibugay
SITE: Brgy. Datu Tumanggong
PROJECT COST: Php 5, 000, 000.00
FUNDS RELEASED: Php 4, 000, 000.00
DATE RELEASED: February 2012
STATUS OF IMPLEMENTATION: Implementation Phase; Construction delayed due to bad weather conditions and consequent delivery problems because of inaccebility roads leading to the project site, Unstable peace and order condition in the project site. -
212271

PROJECT: Junction Dalangin Muslim - Longilog Road
PROVINCE: Zamboanga Sibugay
SITE: Brgys. Dalangin Muslim & Longilog
PROJECT COST: Php 5, 000, 000.00
FUNDS RELEASED: Php 4, 000, 000.00
DATE RELEASED: February 2012
STATUS OF IMPLEMENTATION: Implementation Phase; Construction on-going -
221302

PROJECT: Rehabilitation Tampisilan-Shiolan Brgy. Road
PROVINCE: Zamboanga Sibugay
SITE: Brgys. Tampilisan & Shiolan
PROJECT COST: Php 5, 000, 000.00
FUNDS RELEASED: Php 4, 000, 000.00
DATE RELEASED: February 2012
STATUS OF IMPLEMENTATION: Implementation Phase; Construction delayed due to inaccessibility of road leading to the site. -
467349

PROJECT: Rehabilitation Cawilan-Tuburan Brgy. Road
PROVINCE: Zamboanga Sibugay
SITE: Brgys. Cawilan, Samonte, Moalboal &Tuburan
PROJECT COST: Php 5, 000, 000.00
FUNDS RELEASED: Php 4, 000, 000.00
DATE RELEASED: February 2012
STATUS OF IMPLEMENTATION: Implementation Phase; Construction on-going -
481365

PROJECT: Rehabilitation of Solar-Tambanan, Suba Nipa Brgy. Road
PROVINCE: Zamboanga Sibugay
SITE: Brgys. Solar & Tambanan
PROJECT COST: Php 5, 000, 000.00
FUNDS RELEASED: Php 4, 000, 000.00
DATE RELEASED: February 2012
STATUS OF IMPLEMENTATION: Implementation Phase; Construction delayed due to bad weather conditions and consequent delivery problems because of inaccebility roads leading to the project site.
Agriculture
-
352346

PROJECT: Seaweed Production Project
PROVINCE: Zamboanga Sibugay
SITE: Brgys. Poblacion, Labatan, Katipunan, Minundas, San Roque, Dalama & Mayabo
PROJECT COST: Php 2, 250, 000.00
FUNDS RELEASED: Php 2, 000, 000.00
DATE RELEASED: February 2012
STATUS OF IMPLEMENTATION: Implementation Phase; Implementation activities on-going