BUDGET STATUS

Road and Other Infrastructure
  • 442407

    Project: Concreting of 560m x 4m FMR at Brgy San Isidro in Barcelona

    PROVINCE: Sorsogon

    Site: Brgy. San Isidro, Barcelona

    Project Cost: Php2,800,000.00

    Funds Released: Php2,280,000.00

    Date Released: 3 Aug 2011; 20 March 2012

    Status of Implementation: Completed


     

  • 439391

    Project: Concrete paving of 1,000m FMR from Bactolan, Tiris to San Ramon Burgos road in Casiguran

    PROVINCE: Sorsogon

    Site: Brgy. Tiris and Burgos, Casiguran

    Project Cost: Php3,000,000.00

    Funds Released: Php3,000,000.00

    Date Released: 3 Aug 2011; 15 December 2011

    Status of Implementation: Completed; 1.3 km FMR completed

  • 473390

    Project: Concreting of Buenavista-San Isidro-Batang FMR in Irosin

    PROVINCE: Sorsogon

    Site: Brgy. Buenavista and San Isidro, Irosin

    Project Cost: Php2,500,000.00

    Funds Released: Php2,500,000.00

    Date Released: 3 Aug 2011; 15 June 2012

    Status of Implementation:  Completed; Clearing, grubbing, excavation, and embankment completed
     

  • 400416

    Project: Concrete paving of farm-to-market road from Cogon to San Rafael in Prieto Diaz

    PROVINCE: Sorsogon

    Site: Brgy. San Rafael, Prieto Diaz

    Project Cost: Php3,000,000.00

    Funds Released: Php3,000,000.00

    Date Released: 3 Aug 2011; July 2012

    Status of Implementation:  Completed; Concreting competed, drainage excavation completed, Slope protection works by a grouted riprap completed

  • 446377

    Project: Concrete paving of Tublijon-Sipaya road in Juban

    PROVINCE: Sorsogon

    Site: Brgy. Sipaya, Juban

    Project Cost: Php3,000,000.00

    Funds Released: Php3,000,000.00

    Date Released: 3 Aug 2011; 20 March 2012

    Status of Implementation:  Completed; Construction of 500m line canal and 90 m grouted riprap completed; 745m concreted
     

  • 487310

    PROJECT: Road concreting from Brgy. Real to Brgy. Cantorna, Monreal

    PROVINCE: Masbate

    SITE: Brgy. Cantorna, Monreal, Masbate

    PROJECT COST: Php15,000,000.00

    FUNDS RELEASED: Php12,000,000.00

    DATE RELEASED: 25 June 2012

    STATUS OF IMPLEMENTATION: Implementation Phase - 80%; Construction delayed due to difficulty in hauling materials to the project site.

  • 560314

    PROJECT: Road opening of Umabay Int. - Canahig Road, Mobo

    PROVINCE: Masbate

    SITE: Brgy. Umabay Interior, Mobo, Masbate

    PROJECT COST: Php4,000,000.00

    FUNDS RELEASED: Php3,200,000.00 

    DATE RELEASED: 25 June 2012

    STATUS OF IMPLEMENTATION: Completed

     

     

  • 576325

    PROJECT: Construction of Concrete Girder Bridge in Brgy. Dacu, Mobo

    PROVINCE: Masbate

    SITE: Brgy. Dacu, Mobo, Masbate

    PROJECT COST: Php16,000,000.00

    FUNDS RELEASED: Php12,800,000.00

    DATE RELEASED: 25 June 2012

    STATUS OF IMPLEMENTATION: Implementation Phase; Construction on-going

     

     

  • 397184

    PROJECT: Road concreting in Brgy. Cueva, San Pascual

    PROVINCE: Masbate

    SITE: Brgy. Cueva, San Pascual, Masbate

    PROJECT COST: Php15,000,000.00

    FUNDS RELEASED: Php12,000,000.00

    DATE RELEASED: 25 June 2012

    STATUS OF IMPLEMENTATION: Implementation Phase - 70%; Construction on-going

  • 16688

    PROJECT: Concreting of Malibago-Malaya farm-to-market road in Labo, Camarines Norte

    PROVINCE: Camarines Norte

    SITE: Brgys. Malibago and Malaya, Labo, Camarines Norte

    PROJECT COST: Php40,000,000.00

    FUNDS RELEASED: Php40,000,000.00

    DATE RELEASED: December 28, 2011; 30 September 2012

    STATUS OF IMPLEMENTATION: Completed

     

  • 176115

    PROJECT: Concreting and Gravelling of Exciban-Nalisbitan-Dumagmang Farm-to-Market Road in Labo, Camarines Norte

    PROVINCE: Camarines Norte

    SITE: Brgys. Nalibitan and Dumagmang, Labo, Camarines Norte

    PROJECT COST: Php50,000,000.00

    FUNDS RELEASED: Php50,000,000.00

    DATE RELEASED: December 28, 2011; 30 September 2012

    STATUS OF IMPLEMENTATION: Implementation Phase - 80%; Construction on-going

     

  • 225191

    PROJECT: Concreting of Pambuhan-Lanot Farm-to-Market Road in Mercedes, Camarines Norte

    PROVINCE: Camarines Norte

    SITE: Brgys. Pambuhan and Lanot, Mercedes, Camarines Norte

    PROJECT COST: Php20,000,000.00

    FUNDS RELEASED: Php20,000,000.00

    DATE RELEASED: December 28, 2011; 30 September 2012

    STATUS OF IMPLEMENTATION: Completed

     

  • 186133

    PROJECT: Concreting of Bakiad-Sta. Cruz-Fundado Farm-to-Market Road in Labo, Camarines Norte

    PROVINCE: Camarines Norte

    SITE: Brgys. Bakiad, Sta, Cruz and Fundado, Labo, Camarines Norte

    PROJECT COST: Php10,000,000.00

    FUNDS RELEASED: Php8,000,000.00

    DATE RELEASED: December 28, 2011

    STATUS OF IMPLEMENTATION: PLGU-CN has conducted barangay assemblies as social preparation, bidding to follow

     

  • 149109

    Title: Concreting of Sta. Rosa Sur - San Rafarel Farm-to-Market Road in Jose Panganiban, Camarines

     

    PROVINCE: Camarines Norte

    SITE: Brgy. Sta. Rosa Sur and San rafael, Jose Panganiban, Camarines Norte

    PROJECT COST: Php20,000,000.00

    FUNDS RELEASED: Php20,000,000.00

    DATE RELEASED: December 28, 2011; 30 September 2012

    STATUS OF IMPLEMENTATION: Completed

     

     

Livelihood
  • 438400

    Project: Livelihood Project on Bayong Making

    PROVINCE: Sorsogon

    Site: Gubat, Barcelona, Pto. Diaz, Casiguran, Irosin, Juban and Magallanes

    Project Cost: Php3,700,000.00

    Funds Released: Php2, 960, 000.00

    Date Released: 22 May 2012

    Status of Implementation: Implementation Phase; Awaiting delivery of materials for training to start.

Fisheries
  • 446377

    PROJECT: Marine Reserve and Fish Sanctuary Development Project (Phase I) in Juban

    PROVINCE: Sorsogon

    SITE: Brgy. Sablayan, Juban

    PROJECT COST: Php1,000,000.00

    FUNDS RELEASED: Php 1, 000, 000.00

    DATE RELEASED: August 3, 2011; March 20, 2012

    STATUS OF IMPLEMENTATION: Construction and installation of materials completed

     

Eco-Tourism
  • 473390

    Project: Establishment of Eco-Tourism Center in Irosin

    PROVINCE: Sorsogon

    Site: Irosin

    Project Cost: Php2,000,000.00

    Funds Released: Php2,000,000.00

    Date Released: 3 Aug 2011; 15 June 2012

    Status of Implementation: Completed; Start of construction was delayed due to heavy rains, Repair of existing line canal completed, Base preparation of parking area and stall construction completed

  • 445359

    Project: Improvement of Parola Beach in Magallanes

    PROVINCE: Sorsogon

    Site: Brgy. Behia, Magallanes

    Project Cost: Php2,000,000.00

    Funds Released: Php 2, 000, 000.00

    Date Released: 3 Aug 2011; 3 March 2012

    Status of Implementation: Completed

  • 463372

    Project: Improvement of Bucalbucalan Spring in Magallanes

    PROVINCE: Sorsogon

    Site: Brgy. Aguada Sur, Magallanes

    Project Cost: Php2,000,000.00

    Funds Released: Php 2, 000, 000.00

    Date Released: 3 Aug 2011; 20 March 2012

    Status of Implementation: Completed

  • 443357

    Project: Improvement of Sta. Lourdes Grotto in Magallanes

    PROVINCE: Sorsogon

    Site: Brgy. Behia, Magallanes

    Project Cost: Php1,000,000.00

    Funds Released: Php1,000,000.00

    Date Released: 3 Aug 2011; 20 March 2012

    Status of Implementation: Completed

  • 422404

    Project: Construction of Farmers Market-cum-Tourism Building  (1st Floor) in Gubat

    PROVINCE: Sorsogon

    Site: Brgy. Paradijon, Gubat

    Project Cost: Php4,000,000.00

    Funds Released: Php800,000.00

    Date Released: 3 Aug 2011

    Status of Implementation: Implementation Phase; Construction of 1st floor structure on-going.
     